CAPTION
Panchitas Outfall - Budget 706
1. Approval of Application for Payment No. 4 in the amount of $356,400.00 from Synergy Development pertaining to Construction Contract C-HCDD1-25-037-09-30. Project Engineer HCDD1 Omar Anzaldua Jr., PE, CFM PO#651829
West Main Drain III Extension - Budget 714
2. Approval of Application for Payment No. 4 in the amount of $552,193.20 from Renoworks pertaining to Construction Contract C-HCDD1-24-058-11-06. Project Engineer: S2 Engineering PO#650376
1. Approval of Application for Payment No. 4 in the amount of $356,400.00 from Synergy Development pertaining to Construction Contract C-HCDD1-25-037-09-30. Project Engineer HCDD1 Omar Anzaldua Jr., PE, CFM PO#651829
West Main Drain III Extension - Budget 714
2. Approval of Application for Payment No. 4 in the amount of $552,193.20 from Renoworks pertaining to Construction Contract C-HCDD1-24-058-11-06. Project Engineer: S2 Engineering PO#650376
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 06/16/2026 03:47 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 06/12/2026 01:40 PM
- Final Approval Date:
- 06/16/2026