AI - 104853
8.C.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 09/29/2026
- Submitted By:
- Alvaro Chuc
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Mission McAllen Drain - Budget 712
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-24-057-10-23. Project Engineer B2Z Engineering PO#650255
2. Approval of Application for Payment No. 13 Retainage in the amount of $207,625.93 and $2,039.81 in interest from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-24-057-10-23. Project Engineer B2Z Engineering PO#650255
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-24-057-10-23. Project Engineer B2Z Engineering PO#650255
2. Approval of Application for Payment No. 13 Retainage in the amount of $207,625.93 and $2,039.81 in interest from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-24-057-10-23. Project Engineer B2Z Engineering PO#650255
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/23/2026 04:40 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 09/22/2026 03:38 PM
- Final Approval Date:
- 09/23/2026