AI- 11250
20.C.4.
CC REGULAR
- Meeting Date:
- 09/23/2008
- Submitted For:
- Rocio Villarreal
- Submitted By:
- Rocio Villarreal, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
CAPTION
A. Requesting approval of Change Order No. 4 (additional 40 days) in connection with the "South Tower Park Project" from contracted vendor, Sanchez United Contracting, Inc., and as recommended by project engineer, R. Gutierrez Engineering Corp., with authority for County Judge or Court member to execute document;
B. Requesting approval of Change Order No. 5 (additional 43 days) in connection with the "South Tower Park Project" from contracted vendor, Sanchez United Contracting, Inc., and as recommended by project engineer, R. Gutierrez Engineering Corp., with authority for County Judge or Court member to execute document.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1212-452-00-122-008-0-739
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
POT# 605197 has $117,830.00 available as of 9/18/08.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 09/17/2008 05:40 PM |
| Budget and Management | Veronica Lopez | 09/18/2008 07:39 AM |
| Auditor's Office | 09/19/2008 05:15 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 09/17/2008 04:21 PM
- Final Approval Date:
- 09/19/2008