CAPTION
Hidalgo County Precinct No. 3 for the City of Palmview is requesting approval to amend the professional service contract to Dannenbaum Engineering Company. The original amount of the contract for $19,745.82 will increase in the amount of $6,149.67 for additional services to the Park Drive-Access Road project utilizing recaptured Year 20 (2007) Precinct 3 Street Improvement funds.
BACKGROUND
Dannenbaum Engineering Company bid out and awarded the Park Drive project. The project was later extended to Bentsen Palm Drive to provide access to the Palmview Park which incurred additional costs. Attached for review is an itemized schedule of incurred services and costs. Recommendation to approve by City is also attached for reference.
Original Contract Amount: $ 19,745.82
Amended Amount: $ 6,149.67
Total New Contract: $ 25,895.49
Available Funds: $124,213.89 YR 20 (2007) Pct 3 – Street Improvements (recaptured funds)
Original Contract Amount: $ 19,745.82
Amended Amount: $ 6,149.67
Total New Contract: $ 25,895.49
Available Funds: $124,213.89 YR 20 (2007) Pct 3 – Street Improvements (recaptured funds)
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- Urban County funds
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County Year 20 (2007) Precinct #3- Street Improvement funds will be used for this project.Original Contract Amount: $19,745.82
Amended Amount: $6,149.67
Total New Contract: $25,895.49
Available Funds: $124,213.89 Year 20 (2007) Pct #3- Street Improvements
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 11/25/2008 08:16 AM |
| Auditor's Office | bmorales | 11/26/2008 02:44 PM |
| Purchasing / Internal | 11/26/2008 04:35 PM |
- Form Started By:
- ewebber
- Started On:
- 11/24/2008 04:21 PM
- Final Approval Date:
- 11/26/2008