CAPTION
Requesting approval of Change Order No. 6 (additional sixty (60) days) in connection with the "South Tower Park Project" from contracted vendor, Sanchez United Contracting, Inc., and as recommended by project engineer, R. Gutierrez Engineering Corp., with authority for County Judge or Court member to execute document
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1212-452-00-122-008-0-739
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No Budgetary ImpactAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 12/18/2008 02:11 PM |
| Budget and Management | Veronica Lopez | 12/18/2008 02:55 PM |
| Auditor's Office | 12/19/2008 05:14 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 12/17/2008 05:06 PM
- Final Approval Date:
- 12/19/2008