CAPTION
A. Request approval of Payment Request No. 6 to Ballenger Construction Company for the Construction of Levee DHS Segment 0-5 (1.76 miles).
B. Request approval of Payment Request No. 3 to Ballenger Construction Company for the Construction of Levee DHS Segment 0-6A (2.59 miles).
C. Request approval of Payment Request No. 3 to SER Construction Partners, LTD. for the Construction of Levee DHS Segment 0-6B & 0-6C (1.38 miles).
D. Request approval of Payment Request No. 3 to Zachry Construction Corporation for the Construction of Levee DHS Segment 0-8 (3.31 miles).
E. Request approval of Payment Request No. 3 to McAllen Construction, Inc. for the Construction of Levee DHS Segment 0-9 Ph II (1.75 miles).
F. Request approval of Payment Request No. 5 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-9 Ph I (2.33 miles).
G. Request approval of Payment Request No. 5 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-10 (2.12 miles).
H. Request approval to process manual checks to Ballenger Construction Company, SER Construction Partners, LTD., Zachry Construction Company, McAllen Construction, Inc. and Williams Brothers Construction Company, Inc. for the above mentioned projects pending the approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
I. Request approval of Payment Request No. 7 to Ballenger Construction Company for the Construction of the Mission Levee Improvement Project, Banker Weir to Inspiration Rd.
J. Request approval of Payment Request No. 6 to Ballenger Construction Company for the Construction of the Common Levee/Anzalduas Dike Improvements, Hidalgo Loop Levee to Anzalduas Dam Project.
K. Request approval to process manual checks for the above mentioned projects to Ballenger Construction Company pending completion of the auditing process.
B. Request approval of Payment Request No. 3 to Ballenger Construction Company for the Construction of Levee DHS Segment 0-6A (2.59 miles).
C. Request approval of Payment Request No. 3 to SER Construction Partners, LTD. for the Construction of Levee DHS Segment 0-6B & 0-6C (1.38 miles).
D. Request approval of Payment Request No. 3 to Zachry Construction Corporation for the Construction of Levee DHS Segment 0-8 (3.31 miles).
E. Request approval of Payment Request No. 3 to McAllen Construction, Inc. for the Construction of Levee DHS Segment 0-9 Ph II (1.75 miles).
F. Request approval of Payment Request No. 5 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-9 Ph I (2.33 miles).
G. Request approval of Payment Request No. 5 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-10 (2.12 miles).
H. Request approval to process manual checks to Ballenger Construction Company, SER Construction Partners, LTD., Zachry Construction Company, McAllen Construction, Inc. and Williams Brothers Construction Company, Inc. for the above mentioned projects pending the approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
I. Request approval of Payment Request No. 7 to Ballenger Construction Company for the Construction of the Mission Levee Improvement Project, Banker Weir to Inspiration Rd.
J. Request approval of Payment Request No. 6 to Ballenger Construction Company for the Construction of the Common Levee/Anzalduas Dike Improvements, Hidalgo Loop Levee to Anzalduas Dam Project.
K. Request approval to process manual checks for the above mentioned projects to Ballenger Construction Company pending completion of the auditing process.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 01/23/2009 04:42 PM |
| Final Approval | 01/23/2009 05:21 PM |
- Form Started By:
- mluna
- Started On:
- 01/23/2009 10:01 AM
- Final Approval Date:
- 01/23/2009