Skip to main content

AgendaQuick™

View Agenda Item

AI- 13931
21.B.1.
CC REGULAR
Meeting Date:
02/17/2009
Submitted For:
Marty Salazar
Submitted By:
Vangie Garcia, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Presentation for discussion, consideration and approval of an  "Irrevocable Directive of Draw Proceeds/Disbursement Agreement" as required (as a condition precedent to issuing Payment & Performance bonds) by bonding company, Insurors Indeminity Company, contract surety for Closner Construction for: "Culvert Crossing and Drainange Improvement Project-Mile 13 North and Mile 6 West" (approved by Commissioners Court on January 20, 2009-Project #2008-320B-11-12-LRM)  and thus directing all contract funds to Aacon, Inc., disbursement agent for: Closner Construction Co., LLC and as further specificed/detailed on document(s) attached herein.

BACKGROUND

Approval of this request will allow surety company to provide the required payment and performance bonds for completion and execution of required contracts.

Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1201-431-00-121-052-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Approval for fiscal impact taken on previous action of 01/20/09.

Available Balance as of 2-11-09 ($227,654.66), pending closing of period 13.

Available Balance as of 2-11-09 for calendar year 2008 $571,017.34, pending closing of period 13.

Monies in the amount of $241,000.09 have been appropriated for calendar year 2009 approved by CC on 1-20-09, refer to AI #13405 for the contract award to Closner Construction.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/11/2009 01:21 PM
Budget and Management Veronica Lopez 02/11/2009 01:28 PM
Auditor's Office 02/13/2009 05:45 PM
Form Started By:
vgarcia
Started On:
02/11/2009 09:24 AM
Final Approval Date:
02/13/2009