CAPTION

Presentation for consideration, discussion acceptance and approval of Application for Payment No. 1(final) in the amount of $60,977.79 from Sascon, Inc. contracted vendor for Barney Groves Subdivision submitted by project Engineer Hinojosa Engineering, Inc. C-CAP-08-011-07-11

BACKGROUND


Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1311-431-00-123-072-0-XXX
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO# 610646 has $67,753.10 available as of 2/12/09.

FISCAL YEAR:
9
ACCT. #:
9-1203-431-00-123-005-0-734
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO# 610646 has $67,753.10 available as of 2/12/09.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/12/2009 01:54 PM
Budget and Management Veronica Lopez 02/12/2009 04:04 PM
Auditor's Office 02/20/2009 05:34 PM
Form Started By:
mjackson
Started On:
02/11/2009 05:03 PM
Final Approval Date:
02/20/2009