CAPTION

Requesting approval of Construction  Change Order No. 1 with contracted vendor OG Contruction Company for "Tower Road Drainage Project for the following:
A. an (increase) in the amount of contract in the amount of $6,666.50 for the following items: 1) Add 20 CY of Cement Stabilized Backfill, 2) Add 10 SY of Cut and Restore Pavement, 3) Add 51 LF of RCP CL III Rubber Gasket and 4) Add 2 Manholes Type "A" for a new Storm Sewer Crossing and to avoid force main on items 3 & 4; and,

B.  an additional ten (10) days to time of contract term; and,
with authority for County Judge to execute document.

BACKGROUND

Purchase Order Increase is @ Purchasing Department to reflect Change Order No. 1.


Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1202-431-00-122-031-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funding available in the amount of $12,292.10 as of 04/01/2009.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/02/2009 02:15 PM
Budget and Management Ivan Cantu 04/02/2009 02:46 PM
Auditor's Office 04/03/2009 04:09 PM
Form Started By:
ycisneros
Started On:
04/01/2009 04:17 PM
Final Approval Date:
04/03/2009