CAPTION
a. Requesting approval of Application for Payment #2 in the amount of $193,390.03 in connection with the Tower Road Drainage Project from contracted vendor, OG Construction Company, LLC (C-08-399-02-09) by project engineer, R. Gutierrez Engineering Corporation through contract #C-08-381-09-16 after County Auditor's review and processing procedures are completed including authority for County Treasurer to issue payment(s)/check(s);
b. Requesting approval of Change Order No. 4 in the amount of $4,646.00 and (increase) in 8 days with OG Construction Company (C-08-399-02-09) contracted vendor for "Tower Road Drainage Project" reflecting identified/detailed items, with authority for County Judge to execute document.
c. Requesting approval of Application for Payment #3 in the amount of $67,888.66 in connection with the Tower Road Drainage Project from contracted vendor, OG Construction Company, LLC (C-08-399-02-09) by project engineer, R. Gutierrez Engineering Corporation through contract #C-08-381-09-16 after County Auditor's review and processing procedures are completed including authority for County Treasurer to issue payment(s)/check(s);
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2009
- ACCT. #:
- 9-1339-431-00-122-031-0-733
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding available PO#618129 in the amount $405,369.17 as of 06/17/2009.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 06/17/2009 01:19 PM |
| Budget and Management | Veronica Lopez | 06/17/2009 01:54 PM |
| Auditor's Office | 06/18/2009 05:09 PM |
- Form Started By:
- ycisneros
- Started On:
- 06/17/2009 12:06 PM
- Final Approval Date: