AI- 16376
21.C.1.
CC REGULAR
- Meeting Date:
- 07/14/2009
- Submitted For:
- Marty Salazar
- Submitted By:
- Moises Salazar, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
a. Requesting approval of Change Order No. 1 (Increase of Contract Time) in connection with Precinct No. 2 -"South Tower CRC/Park Pending Construction Items" from contracted vendor, CAS Companies, LP, and as recommended by project architect, V-A Architecture, with authority for County Judge or Court member to execute document.
b. Requesting approval of "Certificate of Substantial Completion" with CAS Companies, LP, reflecting the substantial completion date of July14, 2009 for Precinct No. 2 -"South Tower CRC/Park Pending Construction Items" P.O. 614127.
BACKGROUND
See Attached AIA Documents:
G701-2001 -Change Order.
G704-2000 -Certificate of Substantial completion.
G701-2001 -Change Order.
G704-2000 -Certificate of Substantial completion.
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No fiscal impactAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/10/2009 10:14 AM |
| Budget and Management | Erika Zamora | 07/10/2009 11:46 AM |
| Auditor's Office | 07/10/2009 05:07 PM |
- Form Started By:
- moysalazar
- Started On:
- 07/07/2009 04:23 PM
- Final Approval Date:
- 07/10/2009