CAPTION

Requesting approval of Change Order #1 (net increase) in the amount of $ 4,781.90 in connection with the "Culvert Crossing & Drainage Improvements Project" (Mile 13 North & Mile 6 West) from contracted vendor, Closner Construction Co., LLC (C-08-320B-03-03) and as recommended by project engineer, Dos Logistics Inc., with authority for County Judge or Court member to execute document.

BACKGROUND

Change Order #1-Closner Construciton Co., LLC

Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1339-431-00-121-055-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Amount available in PO #619358 $250,224.85 as of 7/17/09 for CLOSNER CONSTRUCTION CO. Change Order #1 funds pending (AI 15622) in the amount of $4,781.90.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/16/2009 11:30 AM
Budget and Management Erika Zamora 07/16/2009 11:31 AM
Auditor's Office 07/17/2009 05:21 PM