A. Request approval of Change Order No. 18 on the Contract with Ballenger Construction Company for the Construction of DHS Segment 0-6A. Subject to Department of Homeland Security (DHS) concurrence.
B. Request approval of Supplemental #1 to Work Authorization #43 for environmental site assessment as it relates to DHS Segment 0-7A.
C. Request approval of payment of Invoices to Dannenbaum Engineering for professional engineering services in relation to the following DHS Segments:
1. DHS 0-4B Invoice 4287XXF/21/XV
2. DHS 0-4B Invoice 4287XXG/01/XV
3. DHS 0-8 Invoice 441003/15/XV
D. Request approval to process manual checks to Dannenbaum Engineering on the above mentioned projects pending the approval of the County Auditor and pending the electronic transfer of funds from the Department of Homeland Security (DHS).
B. Request approval of Supplemental #1 to Work Authorization #43 for environmental site assessment as it relates to DHS Segment 0-7A.
C. Request approval of payment of Invoices to Dannenbaum Engineering for professional engineering services in relation to the following DHS Segments:
1. DHS 0-4B Invoice 4287XXF/21/XV
2. DHS 0-4B Invoice 4287XXG/01/XV
3. DHS 0-8 Invoice 441003/15/XV
D. Request approval to process manual checks to Dannenbaum Engineering on the above mentioned projects pending the approval of the County Auditor and pending the electronic transfer of funds from the Department of Homeland Security (DHS).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 10/01/2009 04:32 PM |
| Final Approval | 10/02/2009 04:29 PM |
- Form Started By:
- mluna
- Started On:
- 10/01/2009 02:20 PM
- Final Approval Date:
- 10/02/2009