CAPTION
Requesting approval of Construction Change Directive No 2 (Texas Accessability Standards) in connection with the "Completion of Sheriff's Sub-Station Remodeling" in the amount of $ 863.59 from contracted vendor, Jamail Construction, and as recommended by project architect, Alcocer Garcia Associates Design Consulting, with authority for County Judge to execute document. C-04-116-03-23
BACKGROUND
CONSTRUCTION CHANGE DIRECTIVE AMOUNT WILL BE COVERED BY THE CONTINGENCY ALLOWANCE AND WILL NOT CHANGE THE CONSTRUCTION CONTRACT AMOUNT.
Please see attached Change Order #2
P.O. # 574628
Project No. 06-253- JMT
CC approved 09-19-06
Please see attached Change Order #2
P.O. # 574628
Project No. 06-253- JMT
CC approved 09-19-06
Fiscal Impact
- FISCAL YEAR:
- 06
- ACCT. #:
- 6-1332-421-00-120-004-0-452
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
P.O. 574628 has 6471.37 available. Change order is to come from internal project contingency allowance, no additional funding required at this time.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Dina Trevino | 01/04/2007 |
| Auditor's Office | lfong | 01/05/2007 |
| Purchasing / Internal | msalazar | 01/04/2007 |
| Purchasing / Internal | msalazar | 01/04/2007 05:23 PM |
| Budget and Management | Dina Trevino | 01/04/2007 07:31 PM |
| Auditor's Office | lfong | 01/05/2007 03:25 PM |
| Court Administrator |
- Form Started By:
- moysalazar
- Started On:
- 12/28/2006 03:15 PM