AI- 18580
21.E.1.
CC REGULAR
- Meeting Date:
- 11/24/2009
- Submitted For:
- Agapito Vargas
- Submitted By:
- Marcie Jackson, COLONIA ACCESS PROGRAM
- Department:
Information
CAPTION
Acceptance and approval of Change Order No. 1 with contractor Total Commitment, LLC for Esperanza Estates Subdivision, Pct. No. 2 reflecting an increase of $3,000.00 for sewer services adjustments as recommended and submitted through project engineer DOS Logistics, Inc. (C-CAP-09-288-08-04)
BACKGROUND
Contract Price after change order will be $134,181.00.
Fiscal Impact
- FISCAL YEAR:
- 9
- ACCT. #:
- 9-1202-431-00-122-262-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
available balance of $3,000.00 as of 11/18/09.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/18/2009 12:06 PM |
| Budget and Management | Erika Zamora | 11/18/2009 01:21 PM |
| Auditor's Office | lfong | 11/18/2009 04:07 PM |
- Form Started By:
- mjackson
- Started On:
- 11/16/2009 03:19 PM
- Final Approval Date:
- 11/18/2009