1. North Alamo Water Supply:
a. Approximately 500' south of mile 12N on the west side of mile 1.5W- Bore- Antonio Trejo;3/4" serv conn
b. Approximately 1,848' east of FM 1761 on the south side of CR 3200- Line Ext- Bore- 20 ft on driveway two 3/4" service connections- George L. Salazar
c. Approximately 500' north of FM 1925 on the west side of mile 4W- Bore- Jesus Contreras;3/4" serv conn
2. Agua Special Utility District:
a. The contractor proposed to intall an 8" PVC waterline along the North R.O.W. of Veterans Boulevard. Then the 8" P.V.C. water line will run West for 340.0' being 5.0' South of the North R.O.W. line of Veterans Boulevard to the proposed subdivision.
b. Lay 8" PVC water main on the west side and parallel to Western Road in the area between Mile 4 and Mile 5 Roads. A 12" bore will be done crossing (5) Five Mile Line Road, on the west side of Western Road.
3. Rio Delta Engineering:
a. Road Crossing Bore: A 12" PVC water line to be encased with 24" steel casing. Crossing to be located approximately 130 ft. west of the intersection of Rooth Rd and Mile 17 1/2 Rd. (Russell Rd)
b. Road Crossing Bore: An 8" PVC water line to be encased with 16" steel casing. Crossing to be located approximately 1,145 ft. east of the intersection of Rooth Rd and Mile 17 1/2 Rd. (Russell Rd)
c. Road Crossing Bore: A 12" PVC water line to be encased with 24" steel casing. Crossing to be located approximately 105 ft. south of the intersection of Rooth Rd. and Mile 17 1/2 Rd (Russell Rd)
a. Approximately 500' south of mile 12N on the west side of mile 1.5W- Bore- Antonio Trejo;3/4" serv conn
b. Approximately 1,848' east of FM 1761 on the south side of CR 3200- Line Ext- Bore- 20 ft on driveway two 3/4" service connections- George L. Salazar
c. Approximately 500' north of FM 1925 on the west side of mile 4W- Bore- Jesus Contreras;3/4" serv conn
2. Agua Special Utility District:
a. The contractor proposed to intall an 8" PVC waterline along the North R.O.W. of Veterans Boulevard. Then the 8" P.V.C. water line will run West for 340.0' being 5.0' South of the North R.O.W. line of Veterans Boulevard to the proposed subdivision.
b. Lay 8" PVC water main on the west side and parallel to Western Road in the area between Mile 4 and Mile 5 Roads. A 12" bore will be done crossing (5) Five Mile Line Road, on the west side of Western Road.
3. Rio Delta Engineering:
a. Road Crossing Bore: A 12" PVC water line to be encased with 24" steel casing. Crossing to be located approximately 130 ft. west of the intersection of Rooth Rd and Mile 17 1/2 Rd. (Russell Rd)
b. Road Crossing Bore: An 8" PVC water line to be encased with 16" steel casing. Crossing to be located approximately 1,145 ft. east of the intersection of Rooth Rd and Mile 17 1/2 Rd. (Russell Rd)
c. Road Crossing Bore: A 12" PVC water line to be encased with 24" steel casing. Crossing to be located approximately 105 ft. south of the intersection of Rooth Rd. and Mile 17 1/2 Rd (Russell Rd)
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 12/03/2009 08:33 AM |
| Auditor's Office | 12/04/2009 05:01 PM |
- Form Started By:
- Saul Garcia
- Started On:
- 12/01/2009 10:41 AM
- Final Approval Date:
- 12/04/2009