CAPTION
1. G & D Financial Services, L.P. (Pueblo De Palmas at Mile 4 Phase 1):
a. Contractor shall install a 10" water line along the east side of Circle 6th Street West approximately 786 feet North of intersection of Circle 6th Street West & Austen Street. The 10" water line shall continue an addition 3150 feet to connect to an existing 8" water line.
2. Sharyland Water Supply Corporation:
a. Road Crossing (Bore): A 12" PVC waterline to be encased within a 14" PVC casing crossing to be located approximately 100 ft. South of the intersection of Rooth Rd and Mile 17 1/2 Rd.
b. Road Crossing (Bore): A 12" PVC waterline to be encased within a 14" PVC casing crossing to be located approximately 600 ft. East of the intersection of Rooth Rd and Mile 17 1/2 Rd.
c. Road Crossing (Bore): A 1" PVC waterline to be encased within a 2" PVC casing crossing to be located approximately 524 ft South of the intersection of S.H. 107 and Taylor Rd.
a. Contractor shall install a 10" water line along the east side of Circle 6th Street West approximately 786 feet North of intersection of Circle 6th Street West & Austen Street. The 10" water line shall continue an addition 3150 feet to connect to an existing 8" water line.
2. Sharyland Water Supply Corporation:
a. Road Crossing (Bore): A 12" PVC waterline to be encased within a 14" PVC casing crossing to be located approximately 100 ft. South of the intersection of Rooth Rd and Mile 17 1/2 Rd.
b. Road Crossing (Bore): A 12" PVC waterline to be encased within a 14" PVC casing crossing to be located approximately 600 ft. East of the intersection of Rooth Rd and Mile 17 1/2 Rd.
c. Road Crossing (Bore): A 1" PVC waterline to be encased within a 2" PVC casing crossing to be located approximately 524 ft South of the intersection of S.H. 107 and Taylor Rd.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 12/16/2009 09:00 AM |
| Auditor's Office | 12/18/2009 05:12 PM |
- Form Started By:
- Saul Garcia
- Started On:
- 12/11/2009 09:36 AM
- Final Approval Date:
- 12/18/2009