1. Agua Special Utility District:
a. The contractor proposed to bore & install a 16" P.V.C. casing 40.0' L.F. across El Pinto Road for a proposed 8" P.V.C. waterline. The bore will be located 600.0' South of El Sendero Road.
2. The North Alamo Water Supply Corporation:
a. Approximately 1460' west of Goolie Rd on the north and south side of Eldora Rd- Bore- Goolie Meadows Phase III- 8" waterline w/ 16" PVC casing.
a. The contractor proposed to bore & install a 16" P.V.C. casing 40.0' L.F. across El Pinto Road for a proposed 8" P.V.C. waterline. The bore will be located 600.0' South of El Sendero Road.
2. The North Alamo Water Supply Corporation:
a. Approximately 1460' west of Goolie Rd on the north and south side of Eldora Rd- Bore- Goolie Meadows Phase III- 8" waterline w/ 16" PVC casing.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 02/03/2010 08:29 AM |
| Auditor's Office | 02/05/2010 11:44 AM |
- Form Started By:
- Saul Garcia
- Started On:
- 02/02/2010 08:47 AM
- Final Approval Date:
- 02/05/2010