AI- 20384
11.F.
CC CONSENT
- Meeting Date:
- 03/23/2010
- Submitted For:
- Agapito Vargas
- Submitted By:
- Yvette Islas, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
CAPTION
Acceptance and approval of Change Order No. 4 with contractor Closner Construction Co. LC for Citriana Village Subdivision, Pct. No. 2 reflecting an increase to the number of construction period days by six (6) for a total of 169 days due to rain days as submitted through project engineer Cruz-Hogan Consultants-C-CAP-2009-183-05-19.
BACKGROUND
Total contract amount remains the same $322,888.69 -- Total contract period days will now be 169.
Fiscal Impact
- FISCAL YEAR:
- 2010
- ACCT. #:
- 0-1312-431-00-122-154-0-733/734
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No Budgetary Impact.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/17/2010 01:08 PM |
| Budget and Management | Ivan Cantu | 03/17/2010 01:09 PM |
| Auditor's Office | 03/19/2010 03:30 PM |
- Form Started By:
- yislas
- Started On:
- 03/16/2010 01:30 PM
- Final Approval Date:
- 03/19/2010