Approval of final construction contract (awarded by CC on 03-23-10) for C-10-050-03-23 “Hidalgo County Primary Care and Substance Abuse Facility Site and Utility Improvements" between Hidalgo County and The 5125 Company in the amount of $219,512.50.
BACKGROUND
Only two (2) pages of contract (include contract #, awarded vendor name, amount) are provided as back up, due to entire contract being too lengthy. Auditor’s department is provided with one (1) fully executed original contract.
Project Engineer: Quintanilla Headley and Associates, Inc.
Project Engineer: Quintanilla Headley and Associates, Inc.
Fiscal Impact
- FISCAL YEAR:
- 2010
- ACCT. #:
- 0-1100-415-00-115-002-0-841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available as of 4/23/10 $354,845.58.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 04/22/2010 01:50 PM |
| Budget and Management | Erika Zamora | 04/22/2010 02:00 PM |
| Auditor's Office | 04/23/2010 05:00 PM |
- Form Started By:
- moysalazar
- Started On:
- 04/21/2010 02:29 PM
- Final Approval Date:
- 04/23/2010