Skip to main content

AgendaQuick™

View Agenda Item

AI- 21510
23.H.1.
CC REGULAR
Meeting Date:
06/15/2010
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Acceptance and approval of the following items in connection with  Ramon Leal Subdivision with contractor, Closner Construction as submitted through project engineer Izaguirre Engineering Group (C-CAP-09-132-06-08):
a. Application for Payment No. 2 (Retainage Release) in the amount of $9,129.21;
b. “Certificate of Construction Completion” reflecting the completion date of December 2, 2009.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2010
ACCT. #:
0-1200-206-00-123-007-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available funds in P.O. #627746 as of 6/10/10 for Retainage Payable is $381.70.

FISCAL YEAR:
2010
ACCT. #:
0-1312-206-00-000-006-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available funds in P.O. #627746 as of 6/10/10 for Retainage Payable is $8,747.51.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 06/10/2010 08:48 AM
Budget and Management Erika Zamora 06/10/2010 08:53 AM
Auditor's Office lfong 06/11/2010 10:39 AM
Mike Escaname 06/11/2010 05:22 PM
Form Started By:
mjackson
Started On:
06/03/2010 03:45 PM
Final Approval Date:
06/11/2010