AI- 24438
13.I.
CC REGULAR
- Meeting Date:
- 12/21/2010
- Submitted For:
- Hilda Bazan
- Submitted By:
- Estella Webber, URBAN COUNTY
- Department:
- URBAN COUNTY
Information
CAPTION
Requesting approval to re-authorize Urban County Program Director to approve certain Change Orders on Urban County Projects.
BACKGROUND
On January 22, 2002, the Commissioners’ Court granted authority to the Urban County Director to approve Change Orders involving an increase or decrease of $50,000 or less, and for Change Orders requesting additional time for completion.
The County of Hidalgo Procurement Procedures, in Section III, No. F(B), permits as follows:
“If a Change Order involves an increase or decrease in cost of $50,000 or less, the Commissioners’ Court may grant General Authority to an employee to approve the Change Orders. However, the original contract price may not be increased by more than 25 percent unless the Change Order is necessary to comply with a federal or state statute, rule, regulation, or judicial decision enacted, adopted, or rendered after the contract was made.
The original contract price may not be decreased by 18 percent or more without the consent of the contractor.”
The Urban County Program is requesting that such a Grant of General Authority be made to Director Diana R. Serna, under the conditions listed above, and for Change Orders requesting additional time for completion. This would help to speed up project spending and completion, while Commissioners’ Court would still retain responsibility for any proposed major changes.
The County of Hidalgo Procurement Procedures, in Section III, No. F(B), permits as follows:
“If a Change Order involves an increase or decrease in cost of $50,000 or less, the Commissioners’ Court may grant General Authority to an employee to approve the Change Orders. However, the original contract price may not be increased by more than 25 percent unless the Change Order is necessary to comply with a federal or state statute, rule, regulation, or judicial decision enacted, adopted, or rendered after the contract was made.
The original contract price may not be decreased by 18 percent or more without the consent of the contractor.”
The Urban County Program is requesting that such a Grant of General Authority be made to Director Diana R. Serna, under the conditions listed above, and for Change Orders requesting additional time for completion. This would help to speed up project spending and completion, while Commissioners’ Court would still retain responsibility for any proposed major changes.
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Alejandro Garcia | 12/15/2010 03:31 PM |
| Auditor's Office | lfong | 12/17/2010 02:59 PM |
| Purchasing / Internal | 12/17/2010 04:46 PM |
- Form Started By:
- ewebber
- Started On:
- 12/15/2010 11:37 AM
- Final Approval Date:
- 12/17/2010