AI- 25202
7.A.
CC CONSENT
- Meeting Date:
- 02/14/2011
- Submitted For:
- Joe Pena
- Submitted By:
- Sandra Garcia, RIGHT OF WAY DEPT.
- Department:
Information
CAPTION
1. Sanco Development:
a. 12 inch Sewer line will be approximately 1/4 mile north of 3 Mile Line on Moorefield Rd.
2. Magic Valley Electric Cooperative:
a. MVEC will be trenching across Goolie Rd. approx. 400' north of Sioux Rd. from the western right of way line to the eastern right of way line. The trench will contain (2) 6" schedule 40 pvc pipes which will be used to run 6 power line cables. The trench will be approx. 16" wide by 48" deep.
3. North Alamo Water Supply Corporation:
a. Approximately 1300' south of mile 19N on the west side of Kenyon Rd- Bore- Julita Garcia- 3/4"
b. Approximately 500' west of FM 88 on the south side of mile 19N - Bore- Hugo Gonzalez;3/4" serv conn
a. 12 inch Sewer line will be approximately 1/4 mile north of 3 Mile Line on Moorefield Rd.
2. Magic Valley Electric Cooperative:
a. MVEC will be trenching across Goolie Rd. approx. 400' north of Sioux Rd. from the western right of way line to the eastern right of way line. The trench will contain (2) 6" schedule 40 pvc pipes which will be used to run 6 power line cables. The trench will be approx. 16" wide by 48" deep.
3. North Alamo Water Supply Corporation:
a. Approximately 1300' south of mile 19N on the west side of Kenyon Rd- Bore- Julita Garcia- 3/4"
b. Approximately 500' west of FM 88 on the south side of mile 19N - Bore- Hugo Gonzalez;3/4" serv conn
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 02/08/2011 04:43 PM |
| Auditor's Office | 02/11/2011 07:42 AM |
- Form Started By:
- Saul Garcia
- Started On:
- 02/07/2011 02:42 PM
- Final Approval Date:
- 02/11/2011