CAPTION
Approval of final construction contract (awarded by CC on 01-11-11) for C-10-363-01-11 “Tower Road Phase 2 -Road and Drainage Improvements” between Hidalgo County and Mission Paving Co. in the amount of $285,312.10.
BACKGROUND
Only two (2) pages of contract (include contract #, awarded vendor name, amount) are provided as back up, due to entire contract being too lengthy. Auditor’s department is provided with one (1) fully executed original contract. Project Engineer: Raul E. Sesin, PE, Hidalgo County Planning Department
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1342-431-00-122-049-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Pct. 2 -Tower Rd Phase 2;account balance is $448,870.54 as of 2/18/11.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/18/2011 09:08 AM |
| Budget and Management | Erika Zamora | 02/18/2011 09:12 AM |
| Auditor's Office | 02/18/2011 04:26 PM |
- Form Started By:
- moysalazar
- Started On:
- 02/17/2011 05:38 PM
- Final Approval Date:
- 02/18/2011