AI- 25954
11.D.
CC CONSENT
- Meeting Date:
- 04/19/2011
- Submitted For:
- Agapito Vargas
- Submitted By:
- Marcie Jackson, COLONIA ACCESS PROGRAM
- Department:
CAPTION
Requesting approval of the following with contractor H2O Construction Services, Inc. for McKee Subdivision, Pct. No. 1 as submitted through project engineer TEDSI Infrastructure Group Inc. (C-CAP-10-177-06-22):
1. Change Order No. 1 reflecting a decrease totaling the amount of $3,157.92 due to final quantitative adjustments (modified quantities for watering and reduced asphalt unit price);
2. Application for payment No. 2 (Final) in the amount of $24.371.67.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1312-431-00-121-896-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
P.O.# 646591 for H20 Construction Services, Inc. in relation to McKee #1 S/D.Obj. 731 "Roads"-Amount available as of 4-13-11 $30,237.55
Original Contract amount is $117,805.55
Change Order #1 reduction $ (3,157.92), pending CC approval
Revised Contract amount is $114,647.63
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 04/12/2011 03:02 PM |
| Budget and Management | Erika Zamora | 04/12/2011 03:46 PM |
| Auditor's Office | 04/15/2011 09:54 AM |
- Form Started By:
- mjackson
- Started On:
- 03/24/2011 02:42 PM
- Final Approval Date:
- 04/15/2011