- Meeting Date:
- 06/14/2011
- Submitted For:
- Marty Salazar
- Submitted By:
- Marty Salazar, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
a. Presentation by Eli Ochoa, ERO International contracted architect for: (Phase II-Courthouse Property Condition, Environmental Assessments and Needs Analysis and Programming completed in 2009;
b. Information as to recent major repairs and operational related expenditures due to Courthouse age and physical condition;
c. Information as to on-going efforts by Hidalgo County to address deficiencies at the Courthouse;
d. Recommendation by Purchasing Department and administrative staff to engage a professional master planning services provider to review, assess and synthesize all the elements (Courthouse Report by ERO, Historical Commission Report, City of Edinburg, Administration Needs, On-Going Efforts to address critical deficiencies, Etc. related to Courthouse function; if applicable,
e. Discussion and action in connection with possibly entering into an Inter-local Cooperation Agreement with the City of Edinburg for the funding of the master planning services discussed herein;
f. Methods of Engagement:
1. Nominate from County's approved "pool" of architects using the established protocol for selection and engagement;
2. Contract for Master Planning Services provider through our membership/participation with H-GAC;
3. Project specific procurement of a Request for Qualification (RFQ) for the provision of Master Planning Services;
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Budgetary impact on recommendation to engage professional master planning services needs to be addressed by DBM. However, City of Edinburg has made offers to enter into ILA to pay for said services.Funding will be identified prior to contract award. Potential funding source: County-wide contingency.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 06/10/2011 09:54 AM |
| Budget and Management | Erika Zamora | 06/10/2011 10:13 AM |
| Auditor's Office | 06/10/2011 03:22 PM |
- Form Started By:
- msalazar
- Started On:
- 06/07/2011 03:24 PM
- Final Approval Date:
- 06/10/2011