AI- 2716
10.B.
CC REGULAR
Meeting Date:
03/08/2007
Submitted By:
Estella Webber, URBAN COUNTY
Department:
URBAN COUNTY

Information

CAPTION

The City of Elsa requests approval of change order no. 1 to Lambda Construction I, LTD in the amount of $121,520.00 in order to comply with TCEQ requirements utilizing Urban County funding from Water / Sewer Improvements Year 2001 / 2002 / 2003 / 2004 & 2005.

BACKGROUND

Approval of change order no. 1 to Lambda Construction I, LTD in the amount of $121,520.00 for the continuation of improvements to the City of Elsa Water Plant in order to comply with TCEQ requirements.   The amount of the change order is $121,520.00 with the work to be completed by July 30, 2007. 

Original Contract Amount:                        $515,000.00
Change Order Amount:                            $121,520.00
New Contract Amount:                             $636,520.00

Available Funds:
Water / Sewer Improvements             2001             $  23,258.89
                                                       2002                 $  10,977.47
                                                       2003                 $  19,827.77
                                                       2004                 $  65,225.00
                                                       2005            $ 351,222.68

Approval is recommended by the City of Elsa and UCP Staff.


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Dina Trevino 02/27/2007 04:14 PM
Purchasing / Internal msalazar 02/28/2007 03:38 PM
Auditor's Office lfong 03/01/2007 03:50 PM
Court Administrator Monica Salinas 03/02/2007 03:32 PM
Form Started By:
ewebber
Started On:
02/27/2007 10:27 AM
Final Approval Date:
03/02/2007