CAPTION

Presentation of bids received with recommendation from project engineer, Javier Hinojosa for the purposes of award to Valley Boring Service, LLC (low bidder meeting all specifications attached hereto) with a base bid of $73,160.00 for "Drainage Improvements to 2 Mile Line Abram Rd."  36" Dry Bore Method under H.C.I.D. No. 6 Canal and as concurred by Commissioner Joe M. Flores, Hidalgo County Pct. #3-Project #2011-174-07-06-OGG.

BACKGROUND

As reviewed and recommended by Javier Hinojosa Engineering for proposed 36" Dry Bore to 2 Mile Abram Rd. Appropriation of funds under Acct. #1-1339-431-00-123-092-0-733 as per Pct. #3.


Fiscal Impact

FISCAL YEAR:
2011
ACCT. #:
1-1339-431-00-123-092-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Available funds as of 7/14/11 are $100,000.45.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/14/2011 11:30 AM
Budget and Management mmunoz 07/14/2011 11:36 AM
Auditor's Office 07/15/2011 04:40 PM
Form Started By:
Olga Garza
Started On:
07/13/2011 02:33 PM
Final Approval Date:
07/15/2011