AI- 28084
13.A.
CC REGULAR
- Meeting Date:
- 08/22/2011
- Submitted For:
- Pete de la Cruz
- Submitted By:
- Estella Webber, URBAN COUNTY
- Department:
- URBAN COUNTY
Information
CAPTION
Urban County Program is requesting an eighty (80) day contract extension with ASAGO Construction for the construction of sewer improvements in Colonia De Anda & Saenz in Pct. # 1 under the TDRA Colonia Construction Grant # 729055.
BACKGROUND
UCP is requesting approval of an eighty (80) day contract extension due to extenuating circumstances such as that we found that a sewer section of about 680 linear feet that should have connected Colonia De Anda & Saenz to a lift station was not in place. Therefore, the contractor, ASAGO can’t complete the sewer improvements until this section is installed and completed. The additional sewer section will have to be bid out and completed before ASAGO can continue with their sewer improvements. The contract start date is November 30, 2010 and new contract end date will be November 15, 2011.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 08/16/2011 03:41 PM |
| Auditor's Office | aduran | 08/17/2011 02:04 PM |
| Purchasing / Internal | msalazar | 08/17/2011 03:12 PM |
- Form Started By:
- ewebber
- Started On:
- 08/16/2011 02:59 PM
- Final Approval Date:
- 08/17/2011