The Urban County Program on behalf of the City of Alton is requesting approval and award of best and final negotiated contract with Terracon Consultants, Inc. in the amount of $15,100.00 utilizing CDBG Year 22 & 23 (2009 & 2010) Street Improvements funds.
BACKGROUND
Terracon has submitted a best and final offer for construction material testing and geotechnical engineering services for the 2009 & 2010 City of Alton - Street Improvements project. Terracon Consultants, Inc. was the highest ranked firm by County Commissioner’s Court. Contract approval in the amount of $15,100.00. See attached scope of services and Best and Final Offer Letter.
Contract Amount: $ 15,100.00
Funds Available: $ 80,893.69 FY 22 (2009) – Street Improvements
$249,727.00 FY 23 (2010) – Street Improvements
Total: $330,620.69
Contract Amount: $ 15,100.00
Funds Available: $ 80,893.69 FY 22 (2009) – Street Improvements
$249,727.00 FY 23 (2010) – Street Improvements
Total: $330,620.69
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- Urban County Funds
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County Year 22 (2009) & Year 23 (2010) CDBG Street Improvement funds will be utilized for the City of Alton - Street Improvements project.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 08/16/2011 03:41 PM |
| Auditor's Office | Alejandro Garcia | 08/17/2011 10:03 AM |
| Purchasing / Internal | msalazar | 08/17/2011 03:12 PM |
- Form Started By:
- ewebber
- Started On:
- 08/16/2011 03:21 PM
- Final Approval Date:
- 08/17/2011