1.  North Alamo Water Supply:
*  Approximately 500' going West from Milano Rd on the North side of Mile 7N - Bore- Yolanda Ramirez ; 1" meter installation
*  NEC Bush  Rd (CR 3450) Garcia Rd (CR380)- X Rd-  Correa Family Trust - 3/4" meter installation
*  Rambo Est L 2 (SEC Tower/Rogers) - Bore- Alonzo Medina 111- 3/4" meter installation
*  Approximately 3250' going West from FM 493 on Moises Flores Rd from an existing 8" waterline- Line Ext. to service customers for Urban County Program. 

2.  City of Weslaco:  
*  Lay and maintain a 12" sewer line beginning at Mile 6 1/2 W and Tesoro Estates Phase 3, 5' offset along the West ROW line to the Mile 7n.  Along Mile 7N  on the 5' offset from the South ROW line West to the East property line of La Palmas.

3.  Sharyland Water Supply Corporation:
*  A 12" PVC waterline to be encased within a 20" PVC casing, crossing to be located approximately 40ft.  North of the intersection of 4 Mile Line and Bryan Rd.
*  A 12" PVC waterline to begin 20 ft West of the centerline of the intersection of 4 Mile Line & Bryan Rd. then go West for a distance of approximately 2850 ft.  Waterline to be located 5 ft. South of the North ROW line of 4 Mile Line.  

4.  Samson Lonestar Limited Partnership:
*  Install a 6" flowline below Hwy 186 and County Road 5.