CAPTION

Requesting approval of Construction Change Order No. 2 a decrease in the amount of ($3,112.70) with Mission Paving Company, Inc. #C-11-043B-06-28 (contracted vendor for "El Dora Road Improvement Project") reflecting the changes detailed on the change order request with authority for County Judge to execute document.

BACKGROUND

Original Change Order will be corrected to reflect the issuance and effective date of 12/12/11.

Fiscal Impact

FISCAL YEAR:
2011
ACCT. #:
1-1200-431-00-122-052-0-731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Available funds in P.O. #662858 as of 12/8/11 are $128,732.17. No additional funding needed - change order decreases amount by $3,112.70.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 12/07/2011 04:05 PM
Budget and Management mmunoz 12/08/2011 08:10 AM
Auditor's Office Monica Salinas 12/09/2011 08:56 AM
Form Started By:
ycisneros
Started On:
12/07/2011 03:34 PM
Final Approval Date:
12/09/2011