AI- 31050
7.A.
CC CONSENT
- Meeting Date:
- 02/28/2012
- Submitted By:
- Rebecca Gomez, RIGHT OF WAY DEPT.
- Department:
Information
CAPTION
1. North Alamo Water Supply Corporation:
a. Approximately 500' going north from Sioux Rd on the east side of Old La Blanca Rd- Bore- Santos Cerda;3/4" service connection
b. Eldora Ac L11 (SEC Tower/Eldora)- Bore- Herminio Gonzalez- 3/4" service connectiion
2. Agua SUD:
Julia Moreno Acres:
a. The contractor proposes to bore and install 9-1" single water service connections across El Pinto Road. The first bore will be 10-0' south of Siria Street. Second bore will be 270.0' north of Siria Street. Third bore will be 90.0' north of El Lucero Drive. Fourth bore will be 360.0' north of El Lucero St. Fifth bore will be 550.0' North of El Lucero St.
3. Kyndell Bennett of Bennett Investments:
a. Propose 24" concrete storm sewer line under and across Cesar Chavez Road as shown on attachment . "Proposed 24" x 75' R.C.P. CL III Pipe Crossing"
a. Approximately 500' going north from Sioux Rd on the east side of Old La Blanca Rd- Bore- Santos Cerda;3/4" service connection
b. Eldora Ac L11 (SEC Tower/Eldora)- Bore- Herminio Gonzalez- 3/4" service connectiion
2. Agua SUD:
Julia Moreno Acres:
a. The contractor proposes to bore and install 9-1" single water service connections across El Pinto Road. The first bore will be 10-0' south of Siria Street. Second bore will be 270.0' north of Siria Street. Third bore will be 90.0' north of El Lucero Drive. Fourth bore will be 360.0' north of El Lucero St. Fifth bore will be 550.0' North of El Lucero St.
3. Kyndell Bennett of Bennett Investments:
a. Propose 24" concrete storm sewer line under and across Cesar Chavez Road as shown on attachment . "Proposed 24" x 75' R.C.P. CL III Pipe Crossing"
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 02/15/2012 01:02 PM |
| Auditor's Office | aduran | 02/24/2012 09:42 AM |
- Form Started By:
- Rebecca Gomez
- Started On:
- 02/13/2012 03:11 PM
- Final Approval Date:
- 02/24/2012