4.A.
CC CONSENT
- Meeting Date:
- 04/03/2007
- Submitted For:
- Joe Pena
- Submitted By:
- Sandra Garcia, RIGHT OF WAY DEPT.
- Department:
Information
CAPTION
1. Enterprise Texas Pipeline:
* Proposed to open cut Jara Chinas Road to install 10" steel pipeline. Permit granted for 10" pipeline on November 21,2006, open cut was not noted on permit. Will close Jara Chinas Rd for one day and provide alternate access with four flagmen directing traffic.
2. Quintanilla, Headley and Associates, Inc.:
* Said 8" PVC W.L. will be constructed 1320' south of intersection of Mile 11 1/2 North Road and La Blanca Road. Thence 8" PVC W.L. will cross West 60.0 LF with 16" PVC casing bore and installed.
* Said 8" PVC W.L. will be constructed 660' south of intersection of Mile 11 1/2 North Road and La Blanca Road. Thence 8" PVC W.L. will cross West 60.0 LF with 16" PVC casing bore and installed.
3. North Alamo Water Supply:
* Approximately 500' East of Co Rd 3350 on the North side of Co Rd 3385- X Rd- Virgilio Tablo, 3/4" meter installation.
* Approximately 500' East of FM 88 on the South side of Mile 14 1/2 N - Bore- Robert Ruiz, 3/4" meter installation
* La Quinta, 300' North of MIle 11 (East of FM 88) - leak in the middle of road (emergency)
* Earling Rd, 2/10 Mile East of Val Verde - leak in the middle of road (emergency)
* Proposed to open cut Jara Chinas Road to install 10" steel pipeline. Permit granted for 10" pipeline on November 21,2006, open cut was not noted on permit. Will close Jara Chinas Rd for one day and provide alternate access with four flagmen directing traffic.
2. Quintanilla, Headley and Associates, Inc.:
* Said 8" PVC W.L. will be constructed 1320' south of intersection of Mile 11 1/2 North Road and La Blanca Road. Thence 8" PVC W.L. will cross West 60.0 LF with 16" PVC casing bore and installed.
* Said 8" PVC W.L. will be constructed 660' south of intersection of Mile 11 1/2 North Road and La Blanca Road. Thence 8" PVC W.L. will cross West 60.0 LF with 16" PVC casing bore and installed.
3. North Alamo Water Supply:
* Approximately 500' East of Co Rd 3350 on the North side of Co Rd 3385- X Rd- Virgilio Tablo, 3/4" meter installation.
* Approximately 500' East of FM 88 on the South side of Mile 14 1/2 N - Bore- Robert Ruiz, 3/4" meter installation
* La Quinta, 300' North of MIle 11 (East of FM 88) - leak in the middle of road (emergency)
* Earling Rd, 2/10 Mile East of Val Verde - leak in the middle of road (emergency)