Presentation for discussion, consideration and approval of two proposed change orders for the K-mart Building renovations in connection with:
a) one (1) 1000 KW Generator with peripherals; in an amount not to exceed $ 322,399.65; and,
b) Various addition, deletions and modifications (as requested/required by affected departments) in an amount not to exceed $ 63,915.50.
a) one (1) 1000 KW Generator with peripherals; in an amount not to exceed $ 322,399.65; and,
b) Various addition, deletions and modifications (as requested/required by affected departments) in an amount not to exceed $ 63,915.50.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- Y partial
- MATCHING FUNDS Y/N?:
- Y
BUDGETARY IMPACT:
Project's current contingency fund balance is $40,000.00, in addtion the following allowances may be applied: plumbing $2316.00, electrical $ 7,000.00, HVAC $ 15,000.00, site allowance $ 8,000.00; If both propossed change orders are approved an additional $315,000.00 would be required to fully fund the proposed change orders
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/29/2007 09:37 AM |
| Budget and Management | Dina Trevino | 03/29/2007 02:17 PM |
| Auditor's Office | lfong | 04/02/2007 11:46 AM |
| Court Administrator | Monica Salinas | 04/03/2007 04:55 PM |
- Form Started By:
- msalazar
- Started On:
- 03/28/2007 01:51 PM
- Final Approval Date:
- 04/03/2007