Skip to main content

AgendaQuick™

View Agenda Item

AI- 32945
Precinct #2   14.A.
CC REGULAR
Meeting Date:
06/26/2012
Submitted By:
Katia Garcia, COMM. PCT. #2
Department:
COMM. PCT. #2

Information

CAPTION

Presentation for consideration, discussion, acceptance and approval of the following with Saenz Utility Contractors, Ltd. for El Dora Road & Drainage Improvements Project, as submitted and recommended by project engineer R. Sesin;

a. Certificate of Substantial Completion

b. Application for Retainage in the amount of $19,433.68

c. Certificate of Construction Completion reflecting completion date of March 12, 2012

with authority for County Judge or Court member to execute documents

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1200-206-00-122-023-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available balance $18,273.68 pending retainage for Application for Payment #3

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management mmunoz 06/21/2012 03:23 PM
Purchasing / Internal Monica Salinas 06/22/2012 04:26 PM
Form Started By:
Katia Garcia
Started On:
06/21/2012 01:23 PM
Final Approval Date:
06/22/2012