CAPTION

Acceptance and approval of the final construction contract documents (awarded by CC-09-25-12) with STFC, Inc. dba Fresno Construction in the approved amount of $188,710.75 for: "Hidalgo County Precinct No. 4 -Construction of a New Multi Purpose Facility and Mechanical Shop -Civil Site Improvements (C-12-056C-09-25)."

BACKGROUND

Project Purchase Order Requisition No. 224705.

Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1342-431-00-124-07X-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Available balance as of 10-12-12:

Program# Amount
075 $1,002,273.40
078 $ 61,463.85
079 $ 12,083.00

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 10/12/2012 01:28 PM
Budget and Management mmunoz 10/12/2012 01:30 PM
Auditor's Office Alejandro Garcia 10/12/2012 05:08 PM
Form Started By:
moysalazar
Started On:
10/12/2012
Final Approval Date:
10/12/2012