Skip to main content

AgendaQuick™

View Agenda Item

AI- 35986
12.D.
CC CONSENT
Meeting Date:
01/15/2013
Submitted For:
Marty Salazar
Submitted By:
Moises Salazar, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Approval of Request for Payment-Application No. 2 in the amount of $12,628.97 from Holchemont, LTD, awarded contractor for the, "Construction Of New Constable Precinct No. 1 Offices", and as certified for payment by project architect, Alcocer Garcia Associates, Inc.  (C-028-07-24) 

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1336-421-00-220-042-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO # 680750 for Holchemont LTD; funds available as of 1-11-13, pending year end carryovers.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal dbetancourt 01/10/2013 01:54 PM
Budget and Management Obdett Calzada 01/10/2013 02:21 PM
Auditor's Office Alejandro Garcia 01/11/2013 05:24 PM
Form Started By:
moysalazar
Started On:
12/26/2012
Final Approval Date:
01/11/2013