CAPTION
A. Request approval to appropriate proceeds received from the Hidalgo County Drainage District #1 2013 Bond Series - 84,000,000. 2013 Bond Series - fund # 133 in the District's Capital Projects will be created to account for the disbursements of these proceeds as specified in the 2012 Bond Resolution approved on September 4th 2012. Dollar amounts for each project are currently in an undistributed accounts per project. As Projects progress and Engineering and Construction contracts are awarded by the Board, transfer will be made through Board Action.
B. Approval to transfer funds from undistrictributed to specified line items in the follow 2013 Bond Series Projects:
1. Rural Drainage Development - Precinct #3
a. La Joya Water Shed - Engineering - $ 705,552.
2. Rado Drain Re- Route - Precinct #2 - Engineering - $293,457
3. Mission Inlet Re- Certification - Precinct #3 Engineering - $857,568.
4. Rural Drainage Development - Precinct # 4
a. North Seminary States - Engineering - $9,596.42
5. Levee Pumps/ Culvert Structure Improvements :
a. East Donna Drain - Precinct #1 - Engineering - $ 135,310
b. Weslaco Drain Lateral - Precinct #1 - Engineering - $135,310
c. South Mercedes Lateral - Precinct #1 - Engineering - $135,310
d. Mercedes Lateral - Precinct #1 Engineer - $ 135,310.
B. Approval to transfer funds from undistrictributed to specified line items in the follow 2013 Bond Series Projects:
1. Rural Drainage Development - Precinct #3
a. La Joya Water Shed - Engineering - $ 705,552.
2. Rado Drain Re- Route - Precinct #2 - Engineering - $293,457
3. Mission Inlet Re- Certification - Precinct #3 Engineering - $857,568.
4. Rural Drainage Development - Precinct # 4
a. North Seminary States - Engineering - $9,596.42
5. Levee Pumps/ Culvert Structure Improvements :
a. East Donna Drain - Precinct #1 - Engineering - $ 135,310
b. Weslaco Drain Lateral - Precinct #1 - Engineering - $135,310
c. South Mercedes Lateral - Precinct #1 - Engineering - $135,310
d. Mercedes Lateral - Precinct #1 Engineer - $ 135,310.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Alejandro Garcia | 04/05/2013 03:07 PM |
| Final Approval | Alejandro Garcia | 04/05/2013 03:57 PM |
- Form Started By:
- Lora Briones
- Started On:
- 04/05/2013 11:54 AM
- Final Approval Date:
- 04/05/2013