1. Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for construction material testing.
2. Presentation of the scoring grid for the purpose of ranking by Commissioner’s Court of at least three (3) testing firms from the county’s approved “pool” as graded and evaluated by the Precinct No. 1, Urban County Program, and Hidalgo County Purchasing Department, in connection with and funded through Hidalgo County Urban County Program Years 22, 23, 24 & 25 (2009, 2010, 2011 & 2012) Precinct No.1 - Street Improvements funds.
3. Authority to negotiate a professional engineering service contract with the highest ranked firm of
for construction material testing for Urban County Program Years 22, 23, 24 & 25 (2009, 2010, 2011 & 2012) Precinct No.1 - Street Improvements funds.
2. Presentation of the scoring grid for the purpose of ranking by Commissioner’s Court of at least three (3) testing firms from the county’s approved “pool” as graded and evaluated by the Precinct No. 1, Urban County Program, and Hidalgo County Purchasing Department, in connection with and funded through Hidalgo County Urban County Program Years 22, 23, 24 & 25 (2009, 2010, 2011 & 2012) Precinct No.1 - Street Improvements funds.
| Professional Service Firm: | Grade | Ranked |
| MEG Engineers | 95% | |
| TERRACON | 92% | |
| Professional Services Industries, Inc. | 87.67% |
3. Authority to negotiate a professional engineering service contract with the highest ranked firm of
for construction material testing for Urban County Program Years 22, 23, 24 & 25 (2009, 2010, 2011 & 2012) Precinct No.1 - Street Improvements funds.
BACKGROUND
The three testing firms rated from the county’s approved “pool” are: (1) MEG Engineers (2) TERRACON, and (3) Professional Services Industries, Inc. for Precinct No. 1 - Street Improvements - Project – Minnesota Road (from Val Verde Rd. to Dillon Rd) project.
Funds Available:
$ 27,011.15 YR 22 (2009) Street Improvements
$ 37,644.31 YR 23 (2010) Street Improvements
$175,410.80 YR 24 (2011) Street Improvements
$249,441.00 YR 25 (2012) Street Improvements
Total: $489,507.26
Funds Available:
$ 27,011.15 YR 22 (2009) Street Improvements
$ 37,644.31 YR 23 (2010) Street Improvements
$175,410.80 YR 24 (2011) Street Improvements
$249,441.00 YR 25 (2012) Street Improvements
Total: $489,507.26
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Alejandro Garcia | 04/26/2013 08:08 AM |
| Purchasing / Internal | Alejandro Garcia | 04/26/2013 05:18 PM |
- Form Started By:
- Melissa Flores
- Started On:
- 04/25/2013 04:17 PM
- Final Approval Date:
- 04/26/2013