Skip to main content

AgendaQuick™

View Agenda Item

AI- 38675
12.G.
CC CONSENT
Meeting Date:
05/28/2013
Submitted For:
H.C. Sheriff Gdpe.
Submitted By:
Rocio Villarreal, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

1. Approval of Architect's Supplemental Instructions No. 2 (funded from the Allowances/Contingency) in the amount of $13,144.08, to contractor D. Wilson Construction Co., in connection with the "Sheriff's Office Substation in the Pct. 1 Area"-C-11-032-12-13.

2. Approval of Request for Payment-Application No. 12 in the amount of $16,115.87 from D. Wilson Construction Co. awarded contractor for the, "Construction of the Sheriff's Office Substation in the Pct. 1 Area", and as certified for payment by project architect, Gignac & Associates-C-11-032-01-20.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2013
ACCT. #:
3-1336-423-00-280-036-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funding available on PO 670920 as of 5-23-13

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal dbetancourt 05/23/2013 10:29 AM
Budget and Management Obdett Calzada 05/23/2013 11:32 AM
Auditor's Office Monica Salinas 05/24/2013 04:07 PM
Form Started By:
Rocio Villarreal
Started On:
05/08/2013 04:41 PM
Final Approval Date:
05/24/2013