CAPTION
A. Acceptance and approval to increase original PO#680750 for Holchemont LTD. as approved by the Architect of record "Alcocer Garcia Associates" thru AIA Document G701-2001 Change Order #003 in the amount of $28,430.33 for change request as outlined in the Summary Of Change Order No. 3 to include but not limited to installation of Fire Line (FDC), installation of braceings to front porch and tile, for the continuation of construction at Pct. #1 Constable Building; and, in addition;
B. Clarification of Betterment Allowance entry on previous request of AIA Document G701-2001 Change Order #002 erroneously reflected $3,313.89 and has been changed to $3,013.89 which is the corrected amount.
B. Clarification of Betterment Allowance entry on previous request of AIA Document G701-2001 Change Order #002 erroneously reflected $3,313.89 and has been changed to $3,013.89 which is the corrected amount.
BACKGROUND
Proposed Change Order will have no fiscal impact, refer to AI-39579 for decrease of SOW in the amount of $30,929.21 to H&H for proposed Fire Line installation.
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- 3-1342-421-00-220-042-0-XXX
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
NO FISCAL IMPACT; funding to be appropriated from AI-39579 for proposed CO #3 after P.O. (#692410) liquidation has been complete. Transfer of funding to be appropriated by DBM as per Mr. Sergio Cruz.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/12/2013 04:25 PM |
| Budget and Management | Obdett Calzada | 07/12/2013 04:36 PM |
| Merlen P. Munoz | mmunoz | 07/12/2013 05:47 PM |
| Auditor's Office | Monica Salinas | 07/12/2013 05:55 PM |
- Form Started By:
- Olga Garza
- Started On:
- 07/12/2013 03:02 PM
- Final Approval Date:
- 07/12/2013