Skip to main content

AgendaQuick™

View Agenda Item

AI- 4059
14.A.9.
CC REGULAR
Meeting Date:
06/05/2007
Submitted For:
Rocio Villarreal
Submitted By:
Rocio Villarreal, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

A. Requesting approval of Change Order No.6 (Fire Sprinkler Check Valve) in connection with the "Hidalgo County Administration Building" in the amount of $1,278.00 (Repair Allowance from contracted vendor, Joe Williamson Construction Co., and as recommended by project architect,Rike Ogden Figueroa Allex Architects , with authority for County Judge to execute document. C-06-092-07-25; 

B. Requesting approval of revised/amend Change Order No.2 (approved by CC on 3/21/07) in connection with the "Hidalgo County Administration Building" to reflect  amount to be deducted from Allowance Repair submitted from Descon Construction LP, and as recommended by project architect, ROFA Architects with authority for County Judge or Presiding Com. Court Officer to execute.

C.  Approval of correction of Change Order Number (as approved by CC on 5/29/07 as Change Order no. 4) to Change Order No. 5 in connection with the "Hidalgo County Administration Building."

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2007
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No budgetary impact to the county.  Funding is to come from the internal project contingency allowance.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 05/30/2007 05:26 PM
Budget and Management Dina Trevino 05/31/2007 11:07 AM
Auditor's Office lfong 06/01/2007 09:03 AM
Court Administrator Monica Salinas 06/01/2007 09:34 AM
Form Started By:
Rocio Villarreal
Started On:
05/30/2007 09:10 AM
Final Approval Date:
06/01/2007