CAPTION
Right of Way:
1. North Alamo Water Supply Corporation:
* 4 inch Bore 40.0 feet to the west of 1502 Gulf Circle, Edinburg, TX. Pipeline Estates between Terry Road and Tower Road on the North side of Mile 17 North.
2. Melden & Hunt, Inc.:
* (Pueblo de Palmas Phase 15): A proposed 8" Force main shall be installed along and within the north right-of-way of Ramseyer Rd and the force main shall run approximately 5600.00 feet. The force main shall start approximately 202.00 feet East of Cesar Chavez Rd and running West crossing Cesar Chavez Rd, Kenyon Rd and Doolittle Rd then crossing Ramseyer Rd to the south connecting to an existing Sanitary sewer manhole. The contractor shall open cut Cesar Chavez Rd and shall open cut 4 caliche drives and 1 asphalt drive between Cesar Chavez Rd and Kenyon Rd. The contractor shall bore under 3 roads with an 8" bore, one being Kenyon Rd, Doolittle Rd, Ramseyer Rd and 3 additional asphalt drive shall be crossing with an 8" bore, Earth Drive located 1715.00 feet East of Doolittle Rd and Venture Avenue located approximately 465.00 feet East of Doolittle Rd and a driveway entrance located approximately 200.00 feet East of Doolittle Road.
1. North Alamo Water Supply Corporation:
* 4 inch Bore 40.0 feet to the west of 1502 Gulf Circle, Edinburg, TX. Pipeline Estates between Terry Road and Tower Road on the North side of Mile 17 North.
2. Melden & Hunt, Inc.:
* (Pueblo de Palmas Phase 15): A proposed 8" Force main shall be installed along and within the north right-of-way of Ramseyer Rd and the force main shall run approximately 5600.00 feet. The force main shall start approximately 202.00 feet East of Cesar Chavez Rd and running West crossing Cesar Chavez Rd, Kenyon Rd and Doolittle Rd then crossing Ramseyer Rd to the south connecting to an existing Sanitary sewer manhole. The contractor shall open cut Cesar Chavez Rd and shall open cut 4 caliche drives and 1 asphalt drive between Cesar Chavez Rd and Kenyon Rd. The contractor shall bore under 3 roads with an 8" bore, one being Kenyon Rd, Doolittle Rd, Ramseyer Rd and 3 additional asphalt drive shall be crossing with an 8" bore, Earth Drive located 1715.00 feet East of Doolittle Rd and Venture Avenue located approximately 465.00 feet East of Doolittle Rd and a driveway entrance located approximately 200.00 feet East of Doolittle Road.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 06/05/2014 03:48 PM |
| Auditor's Office | Monica Salinas | 06/13/2014 05:37 PM |
- Form Started By:
- Rebecca Gomez
- Started On:
- 06/02/2014 10:49 AM
- Final Approval Date:
- 06/13/2014