CAPTION
Right of Way:
Engelman Irrigation District:
* Purposed installment of 200 ft. of irrigation pipe on Mile 5 1/2 on county road side ditch.
City of Weslaco:
* Weather Heights Phase I: The proposed 8" Sanitary Sewer will begin 200.0' south of Mile 10 North Road and Mile 4 West Road. It will run south along the west side of Mile 4 West Road within existing Right of Way for a distance of 775.0 Feet.