Acceptance and approval of the final construction contract documents for the project: Hidalgo County Pct. #3-Mile 2 North Roadway Reconstruction (CC award-AI# 46415 of 09-23-14) to IOC Company , LLC in the total amount of $1,569,523.71 (Contract No. C-14-153-02-17) with authority to execute contract.

BACKGROUND

contract too large to attach

Fiscal Impact

FISCAL YEAR:
2015
ACCT. #:
5-1315-431-00-123-094-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Estimated Local Participation after EDC adjustment is 1.6% for Construction ($30,372.00) & Construction Engineering and Contingencies ($3,622.00) for a total of: $33,994.00.
Federal and State reimbursements will be submitted to TxDOT once payment applications are approved through CC.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/05/2015 11:40 AM
Budget and Management Veronica Ortiz 02/05/2015 02:13 PM
Auditor's Office Monica Salinas 02/13/2015 05:22 PM
Form Started By:
yislas
Started On:
02/04/2015 08:58 AM
Final Approval Date:
02/13/2015