AI- 48690
Purchasing Department   15.B.
CC CONSENT
Meeting Date:
03/03/2015
Submitted For:
Marty Salazar
Submitted By:
Moises Salazar, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Requesting ratification of Change Order #2 for an extension of 26 calendar days and an additional cost of $547.00 for quantitative changes on concrete work approved and executed by Precinct 2 Commissioner designee for the project Hidalgo County Precinct No. 2 -"Equipment and Maintenance Facility On-Site Civil Improvements Concrete Work" with RDH Site and Concrete, LLC, contract No.: C-14-353-10-14.

BACKGROUND

Change Order was approved and executed to expedite the project process as  per authority CC under AI#46924.

Fiscal Impact

FISCAL YEAR:
2015
ACCT. #:
5-1342-431-00-122-053-0-740
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO# 717154
PO Increase is in process.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/27/2015 05:20 PM
Auditor's Office Monica Salinas 02/27/2015 05:54 PM
Form Started By:
moysalazar
Started On:
02/27/2015 12:00 PM
Final Approval Date:
02/27/2015