AI- 4988
5.A.
CC CONSENT
- Meeting Date:
- 08/14/2007
- Submitted For:
- Joe Pena
- Submitted By:
- Sandra Garcia, RIGHT OF WAY DEPT.
- Department:
CAPTION
1. NORTH ALAMO WATER SUPPLY:
* Capisallo Park Subd L18 B6 (SEC 1E/9N) BORE- Diego Zuniga- 3/4" Serv. Conn.
* Approximately 350' going East from the intersection of Ash St. and FM 88 on the South side - Line- ext. Reyna Martinez - 3/4" serv. conn.
* Approximately 1460' from the intersection of FM 88 and Mile 21 on the South side boring FM 88 from West to East - Line ext - Alvaro Restrepo- 3/4" serv. conn.
2. DAN A. HUGHES CO:
* 4" steel pipe sch 80 gas high pressure @ 1200psi pipe will cross Jara Chinas Rd.
3. L & G Engineering:
* No utility line will be installed two seventy foot borings will be drilled vertically to provide soil strata information.
* Capisallo Park Subd L18 B6 (SEC 1E/9N) BORE- Diego Zuniga- 3/4" Serv. Conn.
* Approximately 350' going East from the intersection of Ash St. and FM 88 on the South side - Line- ext. Reyna Martinez - 3/4" serv. conn.
* Approximately 1460' from the intersection of FM 88 and Mile 21 on the South side boring FM 88 from West to East - Line ext - Alvaro Restrepo- 3/4" serv. conn.
2. DAN A. HUGHES CO:
* 4" steel pipe sch 80 gas high pressure @ 1200psi pipe will cross Jara Chinas Rd.
3. L & G Engineering:
* No utility line will be installed two seventy foot borings will be drilled vertically to provide soil strata information.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Dina Trevino | 08/09/2007 03:04 PM |
| Rey Salazar | Rey Salazar | 08/09/2007 03:32 PM |
| Auditor's Office | 08/10/2007 04:58 PM |
- Form Started By:
- Saul Garcia
- Started On:
- 08/08/2007 08:32 AM
- Final Approval Date:
- 08/10/2007