CAPTION
Acceptance and approval of Change Order No. 8 for additional 19 days due to rain days and dry out days for the months of June and early July, Contract No. C-14-067-06-03 with JCon Construction, LLC as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of the Linn-San Manuel Emergency Services Facilities" with authority for County Judge, or Court Member to execute document.
BACKGROUND
The new projected Substantial completion as per Change Order No. 8 is: July 24, 2015
Fiscal Impact
- FISCAL YEAR:
- 2015
- ACCT. #:
- 5-1301-419-40-124-136-0-730
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
PO#712761Change order has no fiscal impact.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/14/2015 03:05 PM |
| Budget and Management | Veronica Ortiz | 07/15/2015 09:50 AM |
| Auditor's Office | Monica Salinas | 07/17/2015 05:42 PM |
- Form Started By:
- moysalazar
- Started On:
- 07/14/2015 10:33 AM
- Final Approval Date:
- 07/17/2015