9.
DRAINAGE DISTRICT
- Meeting Date:
- 08/18/2015
- Submitted For:
- Jaime Salazar
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
2013 BOND SERIES
A.) Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for Professional Engineering Services.
B.) Presentation of scoring grid of the firms graded through the District's "Pool" of pre-qualified Professional Engineers for the purpose of ranking by the HCDD1 Board of Directors in connection with Professional Engineering Services required for J-09 Drain System.
C.) Pursuant to the Boards approval requesting authority for the Hidalgo County Drainage District No. 1 to negotiate Professional Engineering Services Agreement with the number one ranked firm of ____________________________, for the provision of Professional Engineering Services for J-09 Drain System.
D.) Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for Professional Engineering Services.
E.) Presentation of scoring grid of the firms graded through the District's "Pool" of pre-qualified Professional Engineers for the purpose of ranking by the HCDD1 Board of Directors in connection with Professional Engineering Services required for Donna North Lateral Control Structure & FM 495 Drain Control Structure.
F.) Pursuant to the Boards approval requesting authority for the Hidalgo County Drainage District No. 1 to negotiate Professional Engineering Services Agreement with the number one ranked firm of ____________________________, for the provision of Professional Engineering Services for Donna North Lateral Control Structure & FM 495 Drain Control Structure.
G.) Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for Professional Engineering Services.
H.) Presentation of scoring grid of the firms graded through the District's "Pool" of pre-qualified Professional Engineers for the purpose of ranking by the HCDD1 Board of Directors in connection with Professional Engineering Services required for Pct. 1 Lucero Del Norte Rural Drainage Improvements.
I.) Pursuant to the Boards approval requesting authority for the Hidalgo County Drainage District No. 1 to negotiate Professional Engineering Services Agreement with the number one ranked firm of ____________________________, for the provision of Professional Engineering Services for Pct. 1 Lucero Del Norte Rural Drainage Improvements.
A.) Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for Professional Engineering Services.
B.) Presentation of scoring grid of the firms graded through the District's "Pool" of pre-qualified Professional Engineers for the purpose of ranking by the HCDD1 Board of Directors in connection with Professional Engineering Services required for J-09 Drain System.
| FIRM NAME: | SCORE: | RANK: |
| Tedsi Infrastructure Group | 99 | |
| S&GE Civil Engineers | 95 | |
| Urban Infrastructure Group | 91 |
C.) Pursuant to the Boards approval requesting authority for the Hidalgo County Drainage District No. 1 to negotiate Professional Engineering Services Agreement with the number one ranked firm of ____________________________, for the provision of Professional Engineering Services for J-09 Drain System.
D.) Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for Professional Engineering Services.
E.) Presentation of scoring grid of the firms graded through the District's "Pool" of pre-qualified Professional Engineers for the purpose of ranking by the HCDD1 Board of Directors in connection with Professional Engineering Services required for Donna North Lateral Control Structure & FM 495 Drain Control Structure.
| FIRM NAME: | SCORE: | RANK: |
| Tedsi Infrastructure Group | 93 | |
| Melden & Hunt, Inc. | 89 | |
| Perez Consulting Engineers | 86 |
F.) Pursuant to the Boards approval requesting authority for the Hidalgo County Drainage District No. 1 to negotiate Professional Engineering Services Agreement with the number one ranked firm of ____________________________, for the provision of Professional Engineering Services for Donna North Lateral Control Structure & FM 495 Drain Control Structure.
G.) Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for Professional Engineering Services.
H.) Presentation of scoring grid of the firms graded through the District's "Pool" of pre-qualified Professional Engineers for the purpose of ranking by the HCDD1 Board of Directors in connection with Professional Engineering Services required for Pct. 1 Lucero Del Norte Rural Drainage Improvements.
| FIRM NAME: | SCORE: | RANK: |
| Tedsi Infrastructure Group | 92 | |
| Melden & Hunt, Inc. | 88 | |
| Perez Consulting Engineers | 86 |
I.) Pursuant to the Boards approval requesting authority for the Hidalgo County Drainage District No. 1 to negotiate Professional Engineering Services Agreement with the number one ranked firm of ____________________________, for the provision of Professional Engineering Services for Pct. 1 Lucero Del Norte Rural Drainage Improvements.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 08/14/2015 08:20 AM |
| Final Approval | jalejos | 08/14/2015 04:44 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 08/13/2015 05:03 PM
- Final Approval Date:
- 08/14/2015